5 years of SPIRAL2 LINAC operation: cryogenic and superconducting RF aspects

MOB06
22 Sept 2025, 12:40
20m
Ito International Research Center

Ito International Research Center

Tokyo
Board: MOB06
Invited Oral Presentation MC1: SRF Facilities Monday Oral Session: B

Speaker

Muhammad Aburas (Grand Accélérateur Nat. d'Ions Lourds)

Description

The superconductor linear accelerator LINAC of SPIRAL2 at the GANIL facility is in operation since October 2019. The 26 superconducting quarter wave resonators (QWR) of the LINAC are integrated into 19 cryostats and cooled down at 4 K by a dedicated refrigeration system. These superconducting cavities are operated at a nominal gradient of 6.5 MV/m but most of the cavities can be operated up to 8 MV/m. One of the 26 cavities shows abnormal energy dissipation at medium and high RF gradient. In this paper, we will present the evolution of the superconducting cavities and the main issues that happened to the superconducting LINAC and its cryogenic system during the last six years and their effects on the beam schedule.

I have read and accept the Privacy Policy Statement Yes

Author

Muhammad Aburas (Grand Accélérateur Nat. d'Ions Lourds)

Co-authors

Dr Adnan Ghribi (Grand Accélérateur Nat. d'Ions Lourds) Jean-François Leyge (Grand Accélérateur Nat. d'Ions Lourds) Mr Marco Di Giacomo (Grand Accélérateur Nat. d'Ions Lourds) Pierre-Emmanuel Bernaudin (Grand Accélérateur Nat. d'Ions Lourds)