The PETRA IV project at DESY in Hamburg aims for a new, 4th generation light source with first light in 2032. It comprises the installation of a completely new, 2.3km long 6GeV electron storage ring and a new injection chain, installation and refurbishment of 31 photon beam lines with 60 end stations, and the construction and refurbishment of 49 buildings including a new 600m long underground experimental hall.
The project will reuse existing tunnels and halls of the PETRA III light source, and targets a dark time without beam of only 30 months, which is a challenging task that requires thorough planning. To meet this challenge, a comprehensive CAD model has been set up that integrates the data of all participants: construction, photon science, accelerator, campus and logistics.
The model comprises representations of all systems and subsystems in different abstraction levels. A strict structure aligned with the project’s WBS and PBS, extensive use of interfaces, and a focus on review and change management processes ensure that the model is complete, consistent and correct and will remain so throughout the entire life cycle of the project.
| Paper status | Proceeding files received |
|---|