17–22 May 2026
C.I.D
Europe/Zurich timezone

Machine physics studies for the MYRRHA Phase 1 linac at SCK CEN

THP4056
21 May 2026, 16:00
2h
C.I.D

C.I.D

Deauville, France
Board: Thursday wine: WB22
Poster Presentation MC4.A17: Hadron accelerators: High Intensity Accelerators Poster session

Speaker

Lennert De Keukeleere (Belgian Nuclear Research Centre)

Description

At the Nuclear Research Center SCK CEN in Belgium, the first phase of the MYRRHA project (an accelerator driven system) is under construction. Included in MYRRHA Phase 1 are a normal conducting injector linac (RFQ + CH cavities) and a super conducting linac (60 single spoke cavities), providing a CW proton beam of 4 mA and 100 MeV.
In this contribution the recent changes to the MYRRHA Phase 1 linac design and the associated machine physics studies are reported. First of all, the layout of the MYRRHA linac was changed from two identical injector linacs each including a dog leg to one straight injector (for the MYRRHA phase 1) and a (future) second injector with a dogleg. The beam dynamics studies of the straight linac and two options for the second injector are presented. Secondly, the impact of a detailed mechanical integration of the beam line elements, which is a compromise between the ideal theoretical layout and a realistic and pragmatic implementation, on the longitudinal and transverse phase space distributions is discussed. Finally, the losses along the linac and their relation to the RFQ output distribution are presented.

Paper status Proceeding files received

Authors

Jarno Van De Walle (Belgian Nuclear Research Centre) Lennert De Keukeleere (Belgian Nuclear Research Centre)

Co-authors

Mr Eugene Tanke (Belgian Nuclear Research Centre) Jeroen Hustings (Belgian Nuclear Research Centre) Ulrich Dorda (Belgian Nuclear Research Centre)

Presentation materials