Successful cleanroom installation of PIP-II SSR2 coupler using robotic arm

MOPB056
26 Aug 2024, 16:00
2h
Boulevard (Hilton Chicago)

Boulevard

Hilton Chicago

720 South Michigan Ave Chicago, IL 60605 USA
Poster Presentation MC4.8 Superconducting RF Monday Poster Session

Speaker

Colin Narug (Fermi National Accelerator Laboratory)

Description

To minimize the contamination of SRF cavities, remote installation techniques are needed during the installation of components. Recent work at Fermilab has been performed to begin the process of developing techniques for assembling cavities using robotics. Multiple alignment methods were prototyped including alignment and computer vision methods. Using a remotely controlled robotic arm, the alignment and installation of couplers have been successfully performed on prototype PIP-II SSR2 cavities in a cleanroom. The installation process will be shown to show to demonstrate the potential of future installations on other cavities and cavity ancillaries.

Funding Agency

This manuscript has been authored by Fermi Research Alliance, LLC under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy, Office of Science, Office of High Energy Physics.

Primary author

Colin Narug (Fermi National Accelerator Laboratory)

Co-authors

Alessandro Ciaramella (University of Pisa) Caleb Denton (Northern Illinois University) Damon Bice (Fermi National Accelerator Laboratory) Donato Passarelli (Fermi National Accelerator Laboratory) Genfa Wu (Fermi National Accelerator Laboratory) Josh Helsper (Fermi National Accelerator Laboratory) Mattia Parise (Fermi National Accelerator Laboratory) Tommaso Aiazzi (Fermi National Accelerator Laboratory)