Speaker
Description
This paper reports the status and recent progress of INFN LASA’s in-kind contribution to the PIP-II project at Fermilab, with updates on key activities and major procurements. Production efforts for the 38 INFN LASA-designed, 5-cell cavities (β=0.61) for the LB650 section of the linac are underway and two pre-series prototypes are being realized as a first step to validate the manufacturing and treatment sequence. Concurrently, preliminary testing on existing prototypes is progressing to gain a deeper understanding of the surface preparation and qualification procedures, including cross-validation at different infrastructures. Series LB650 cavities will be industrially produced and surface-treated to achieve the stringent performance targets, qualified via vertical cold tests at DESY AMTF, and delivered installation-ready for string assembly.